Update KJ The Hague #5: the baseboard is ready


The baseboard is ready
At the beginning of October, we poured the last part of the 5th floor slab. Structurally, we have now completed the most complicated phase. From now on, the towers will really start to take shape.

At the Park Tower, we are now on the 9th floor. By the end of this year, we aim to exceed 50 meters in height. The tower on the Nieuw Babylon side is slightly behind schedule but progressing as planned.

Work on the facade has started
In early October, the first facade elements were assembled in the factory. Recently, the first elements arrived in The Hague and were installed. You can see this clearly on the Rijnstraat side. The facade is not yet complete; next year, we will install the characteristic vertical concrete strips.

The final sprint has already begun
Once the building is sufficiently wind and watertight, we will start with the interior finishing. The observant viewer may have already seen the packs of plaster on the floors. The ambition is to start installing the first interior walls around Christmas.

 

Our working hours are typically from 07.00 to 16.00 hrs
According to the building permits, we are allowed to work from Monday to Saturday between 07.00 and 19.00 hrs. In practice, this is usually from Monday to Friday from 07.00 to 16.00 hrs. Occasionally, we may need to work outside of the permitted hours. In such cases, we always coordinate with the municipality and inform you in advance.

Updates about the construction at www.wijbouwen.nu/kjdenhaag
Approximately every quarter, we publish a message here with the latest construction updates from KJ Den Haag.

If you notice anything or have any questions
Feel free to email us at kj@jpvaneesteren.nl or speak to our construction site manager Eric van Nes. He is almost daily at the construction site. In case of emergencies, we are available day and night at phone number 088 – 923 69 92.

P.S. Deze update is ook beschikbaar in het Nederlands.


Bekijk ook

Uw contactpersoon

Eric van Nes

Andere berichten

Update KJ Den Haag #7: hoogste punt is in zicht

Het hoogste punt is in zicht! Bij de Parktoren stortten we onlangs de...

Update KJ Den Haag #7: the highest point is in sight

The highest point is in sight! At the Park Tower, we recently poured...

Update KJ The Hague #6: We're halfway there

We are halfway there At the Park Tower, we are over the halfway mark!...

Update KJ Den Haag #6: we zijn halverwege

We zijn halverwege Bij de Parktoren zijn we over de helft! Vorige week...

Update KJ Den Haag #5: de plint is klaar

De plint is klaar Begin oktober stortten we het laatste deel van de 5e...

Update KJ Den Haag #4: we gaan de lucht in

We zijn met de bouw inmiddels op verdieping 4 Sinds een paar weken...

Update KJ The Hague #4: up in the air

We have now reached the fourth floor with the construction For a few...

Update KJ The Hague #3: 600 tons of steel assembled

Team KJ is almost 5 months in It feels like just yesterday we were...

Update KJ Den Haag #3: al 600 ton staal gemonteerd

Team KJ is bijna 5 maanden onderweg Het voelt als de dag van gisteren...

Update KJ Den Haag #2 | De bouw is gestart

De bouw van KJ Den Haag is gestart. Graag geven we u een update van de...

Informatiebrief #1

Beste meneer, mevrouw, Binnenkort starten we met bouwen van KJ Den...

Informatiebijeenkomst KJ Den Haag

Wilt u zich aanmelden voor de informatiebijeenkomst? Dat kan tot en...