KJ

Den Haag

Update KJ Den Haag #9: highest point and facade becoming visible


The first highest point has been reached
Earlier this month, we celebrated reaching the highest point of the Park Tower. With the placement of the final steel structure, we reached a height of nearly 93 meters! Meanwhile, work on the 27th floor of the Station Tower is progressing rapidly. After the summer holidays, we’ll be able to celebrate the highest point there as well.
 

The final façade is becoming visible
Most of the façade is still black for now—that’s the waterproof membrane. But on the Rijnstraat side, we’re slowly starting to see what KJ The Hague will actually look like. There, we’ve begun installing the concrete fluted elements and balconies. Part of the façade is being mounted at night.

More on this in update #8.

Busy times next door
KJ The Hague is being built right up against the Stichthage building. That’s why the station building is also getting a new façade on its lower two floors. One by one, we’re replacing the existing storefronts with the new façade. To ensure safe working conditions, one of the two entrances is currently closed. We expect to finish in the beginning of the fourth quarter, after which that entrance will reopen. To replace the final section of the Stichthage façade, the other entrance will then be closed. The bicycle parking will remain open throughout; more on that later.

City entrance gets attention
Upon completion, the wooden ceiling beneath the building will be a true eye-catcher. But there’s still a lot to be done before we get there. If you peek over the construction fence, you’ll see the outlines of the shops slowly taking shape. In the first section, we’re now putting the finishing touches on the installations. Shortly after the summer holidays, we’ll begin constructing the wooden ceiling.


Bekijk ook

Uw contactpersoon

Eric van Nes

Andere berichten

Update KJ Den Haag #9: hoogste punt bereikt en gevel wordt zichtbaar

Eerste hoogste punt is bereikt Begin deze maand vierden we het...

Update KJ Den Haag #8: aankondiging nachtelijke werkzaamheden

Beste omwonende/ondernemer, We zijn hard bezig met het aanbrengen...

Update KJ Den Haag #8: announcement of night-time work

Dear resident/business owner, We are currently working hard on...

Update KJ Den Haag #7: hoogste punt is in zicht

Het hoogste punt is in zicht! Bij de Parktoren stortten we onlangs de...

Update KJ Den Haag #7: the highest point is in sight

The highest point is in sight! At the Park Tower, we recently poured...

Update KJ The Hague #6: We're halfway there

We are halfway there At the Park Tower, we are over the halfway mark!...

Update KJ Den Haag #6: we zijn halverwege

We zijn halverwege Bij de Parktoren zijn we over de helft! Vorige week...

Update KJ Den Haag #5: de plint is klaar

De plint is klaar Begin oktober stortten we het laatste deel van de 5e...

Update KJ The Hague #5: the baseboard is ready

The baseboard is ready At the beginning of October, we poured the last...

Update KJ Den Haag #4: we gaan de lucht in

We zijn met de bouw inmiddels op verdieping 4 Sinds een paar weken...

Update KJ The Hague #4: up in the air

We have now reached the fourth floor with the construction For a few...

Update KJ The Hague #3: 600 tons of steel assembled

Team KJ is almost 5 months in It feels like just yesterday we were...

Update KJ Den Haag #3: al 600 ton staal gemonteerd

Team KJ is bijna 5 maanden onderweg Het voelt als de dag van gisteren...

Update KJ Den Haag #2 | De bouw is gestart

De bouw van KJ Den Haag is gestart. Graag geven we u een update van de...

Informatiebrief #1

Beste meneer, mevrouw, Binnenkort starten we met bouwen van KJ Den...

Informatiebijeenkomst KJ Den Haag

Wilt u zich aanmelden voor de informatiebijeenkomst? Dat kan tot en...