Information letter #5 Heineken Hoek: work performed and basement walls


Dear businesses and residents,

In this fifth information letter, we would like to let you know about the current situation, what work will be carried out in the coming period, and how this might affect you.

Work performed

  • The basement floor has been poured;
  • We started with the preparing activities for the pouring of the concrete for the basement walls.

Pouring of the basement walls and activities in the coming period
On April 26, the basement floor of the Heineken Hoek has been poured. The concrete mixers were ready at 07:00 and at 12:00 the whole basement floor was poured. Together with the projectteam and our traffic controllers we made sure everything went smoothly. On Friday July 1, the concrete basement walls will be poured till approximately 16:00. We got a permit from the municipality of Amsterdam.

Structural work phase
We are now working hard at the shell of the building. As always, will do our utmost to keep disruption to a minimum. For example, large vehicles will load and unload inside the construction fences whenever possible.

Considerate constructors
We realise that we are guests in your area, and we will try to prevent any nuisance as much as possible and to keep it to a minimum. As a construction company, we are affiliated with the Stichting Bewuste Bouwers (Considerate Constructors Foundation). We work according to its code of conduct, in which limiting nuisance to the environment is paramount.

Our working hours
According to the building permits, work is allowed from Monday to Friday between 07:00 and 16:00. Materials and equipment may be supplied to and removed from the construction site between 07:00 and 12:00. Occasionally, it is possible that we will have to work outside the permitted times. We will let you know if this is the case and it concerns
work that might cause a nuisance.

More information, questions and complaints
For more information about the work on the Heineken Hoek, please go to https://www.wijbouwen.nu/heineken-hoek. Here you will find the latest news, construction updates and an overview of the information letters that have been sent. For more information about this letter and any questions/complaints about the work, please send an e-mail to heinekenhoek@jpvaneesteren.nl. You can also speak to our foreman André Wijbenga, who is present on the construction site every day. In the case of an emergency, we can be reached day and night by calling 0900 824 3473 (TBI-direct).

Kind regards,

Caransa Groep B.V.
J.P. van Eesteren B.V. – 'Heineken Hoek’ Implementation Team


Bekijk ook

Uw contactpersoon

Gerard van Mourik

Andere berichten

Informatiebrief #12 Heineken Hoek: demontage torenkraan en hoogste punt

Beste ondernemers en bewoners, Met deze twaalfde informatiebrief...

Information letter #12 Heineken Hoek: dismantling tower crane and celebration of the highest point

Dear businesses and residents, In this twelfth information letter,...

Informatiebrief #11 Heineken Hoek: start afbouw en gevel

Beste ondernemers en bewoners, Met deze elfde informatiebrief...

Information letter #11 Heineken Hoek: start of construction and facade

Dear businesses and residents, In this eleventh information letter,...

Informatiebrief #10 Heineken Hoek: stort verdiepingsvloer en opbouw steiger

Beste ondernemers en bewoners, Met deze tiende informatiebrief...

Information letter #10 Heineken Hoek: pouring the floors and building the scaffolding

Dear businesses and residents, In this tenth information letter, we...

Informatiebrief #9 Heineken Hoek: kerstvakantie en vooruitblik 2023

Beste ondernemers en bewoners, Met deze negende informatiebrief...

Information letter #9 Heineken Hoek: Christmas holiday and preview 2023

Dear businesses and residents, In this ninth information letter, we...

Informatiebrief #8 Heineken Hoek: plaatsen wanden en trappen

Beste ondernemers en bewoners, Met deze achtste informatiebrief...

Information letter #8 Heineken Hoek: placing walls and stairs

Dear businesses and residents, In this eighth information letter, we...

Informatiebrief #7 Heineken Hoek: stempelramen en damwanden

Beste ondernemers en bewoners, Met deze zevende informatiebrief...

Information letter #7 Heineken Hoek: stemp frames and sheet piles

Dear businesses and residents, In this seventh information letter,...

Informatiebrief #6 Heineken Hoek: plaatsen vloeren en constructie

Beste ondernemers en bewoners, Met deze zesde informatiebrief...

Information letter #6 Heineken Hoek: placing floors and construction

Dear businesses and residents, In this sixth information letter,...

Informatiebrief #5 Heineken Hoek: uitgevoerde werkzaamheden en stort kelderwanden

Beste ondernemers en bewoners, Met deze vijfde informatiebrief...

Information letter #4 Heineken Hoek: work performed and basement floor

Dear businesses and residents, In this fourth information letter, we...

Informatiebrief #4 Heineken Hoek: uitgevoerde werkzaamheden en stort keldervloer

Beste ondernemers en bewoners, Met deze vierde informatiebrief...

Update Heineken Hoek #1: tower crane assembly

Dear businesses and residents, With this update we would like to...

Update Heineken Hoek #1: opbouw torenkraan

Beste ondernemers en bewoners, In deze update geven wij jullie meer...

Information letter #3 Heineken Hoek: Work performed and assembly of tower crane

Dear businesses and residents, In this third information letter, we...

Informatiebrief #3 Heineken Hoek: uitgevoerde werkzaamheden en opbouw torenkraan

Beste ondernemers en bewoners, Met deze derde informatiebrief...

Herbouw Heineken Hoek gestart

Fotografie: Bert RietbergBouwbedrijf J.P. van Eesteren is gestart met...

Informatiebrief #2 Heineken Hoek: planning en start ruwbouw

Beste ondernemers en bewoners, In de eerste informatiebrief stelden...

Informatiebrief #1 Heineken Hoek: start en planning

Beste ondernemers en bewoners, Graag stellen wij ons aan u voor. Wij...